Purchasing Using Vendor Contracts

Note

Review Creating and Managing Vendor Contracts for detail on this topic.

There are two methods to purchase into Lots in HomeBuilder (allocate costs into Lots).

  • Vendor Contracts using Construction Items.
    • You purchase only items at prices that were pre-agreed.
    • This uses Construction Items (pre-setup in the Lot Planning Lines).
  • Ad-Hoc Purchasing.
    • Cost Detail Codes to automate bringing in the correct GL and setup.
    • Purchase any Construction Items against the Lot.
    • This method is explained in the article Ad-Hoc Purchasing.

Vendor Contracts using Construction Items

Search Purchase Invoices and create a new Purchase Invoice (standard BC functionality) and then on the Purchase Invoice Page:

  • Click on the Actions button and then on the Button “Populate from Planning Lines”.
  • Enter the Phase and Contract No. and click OK to open the page below, select the lines you want to bring in, and click on “Add Selected to Purchase Lines”.
    • Note: additional options only come into play if you are using the scheduling options.

Note

If you do not see a Vendor Contract No. when you drill up on the field circled above, then you have two options:

  • Create a Vendor Contract + Revision and add Items to the Contract.
  • Ad-hoc purchasing.
  • Back on the Purchase Invoice you will see the lines that came in. Repeat the previous process as often as you like to bring in new lines.
  • Update the Direct Unit Cost Excl. Tax to match the vendor invoice
    • Decrease with no problem.
    • To increase you must either add a new Planning Line or adjust the Total Cost of the existing line.
  • Post the invoice when you are ready.

“Vendor Contract” Concepts and Suggested Setups

Vendor Contracts are usually created when you have a pre-agreed price to complete a specific piece of work.

  • It is not necessary to have a price and there is still value in creating a Vendor Contract just to indicate which vendor will work on the specific item.
  • Although not necessary; you may find it useful to have one series of Vendor Contracts for Base Contract Items and a different series for Upgrades and Extras.
  • You access Vendor Contracts through:
    • Phases (Search: Phases).
  • You can see the Vendor Contract No. in:
    • Model Items.
    • Phase Items.
    • Phase Planning Lines.
    • Lot Planning lines.
  • You should have a “default” Vendor Contract on a Phase Item.
    • This default Vendor Contract is to be the default for ALL the models in this Phase.
    • This default is copied to the Lot (Planning Lines) when you either:
      • Site the Model on the Lot OR
      • Release the Lot Selection Package.
    • Note that any Item e.g., Hardwood Floor may belong to multiple Vendor Contracts however you may still only have one default against a specific Phase.

 

TroubleShooting

I Cannot Process (Post) a simple Purchase Invoice – I want to Just Make it Work for all Lots in this Phase –

This error relates to the Budget.

Solution: you must mass update Budgets for all the Lots.

  • Search Lots, then select all the Lots (e.g., in a complete Phase) to which you may wish to post purchases.
  • Afterwards, select Actions, then Add Budget Revision.

  • The next step: from the Cost Details page, select all and click on “Push to Lots” as shown below. When the next screen appears, choose all Lots (e.g., in a complete Phase) and click on the “Push to Lots” button.

Change to Setup Part Way Through: I Added New House Areas to my Model and/or Item

Solution: update any information not under Construction.

  • Search House Areas, then Create the House Area in page House Areas.

    • Not mandatory: add the House Area Measurement to the sub-table.
  • Search Models, then select Model Items. From Model Items find the Items that you want to update:

    • Click on “Applicable House Areas”
    • Add the House Area.
    • Back on the Model Items Click on the Add Items button.
    • Select the Item and Click OK.

Change the Vendor Contract mid-way through a project

Example: "I’m Changing Vendor".

If you have already started work on Lots and need to change the Vendor Contract do as follows:

  • Search Phases, then select Planning lines Action Button.
  • Select The Planning Lines that you want to assign a new Vendor, then click Assign Vendor Contract Action Button.
  • On the following screen you will be able to select a Vendor and a contract for the selected Planning Lines.